Board approves 45-meter pool concept for LBHS Pool Modernization
Vote 5-0
The board voted 5-0 to approve the 45-meter pool concept and authorize staff to proceed with the next steps in the design process for the LBHS Pool Modernization project. Nine community members addressed the board during public comment on the item. Clerk Osborne reported that after multiple conversations following the August 2024 reopening of negotiations with the City of Laguna Beach, the City had decided not to participate financially in the pool project and would investigate locations for a second pool. This is the genesis vote for the pool modernization that became a major General Fund pressure across the 2025-26 budget cycle.
People referenced
Citations (1)
- Laguna Beach Unified School District · 2024-10-10
Approved minutes capture Clerk Osborne's update on the City's August 2024 reopened pool-partnership negotiations and the City's subsequent decision not to participate financially.